(A) Delivery cycle time = Wait time + Throughput time
28 days = Wait time + 16 days
Wait time = 28 days - 16 days
= 12 days
(B) MCE = Process time / Throughput time
0.30 = Process time / 16 days
Process time = 16 days * 0.30
= 4.8 days
(C) Throughput time = Process time + Inspection time + Move time + Queue time
16 days = 4.8 days + Inspection time + 0.6 days + 3 days
Inspection time = 16 days - 4.8 days - 0.6 days - 3 days
= 7.6 days
.